Lane closures on Interstate 5 and State Route 516 in SeaTac, Des Moines and Kent continue Monday, Nov. 17 through the morning of Friday, Nov. 21. The lane closures on I-5 will allow crews to pave the road and prepare to install noise walls. The lane closures on SR 516 will allow crews to plant alongside the roadway.

This work is part of the SR 509 Completion Project.

I-5 lane closure information 

Tuesday, Nov. 18 through the morning of Wednesday, Nov. 19

  • 9:30 p.m. to 4 a.m. – Up to three lanes of northbound I-5 will close overnight between South 272nd Street (Exit 147) and SR 516 (Exit 149).

Wednesday, Nov. 19 through the morning of Friday, Nov. 21

  • 9:30 p.m. to 4 a.m. – Up to two lanes of northbound I-5 will close nightly between South 272nd Street (Exit 147) and SR 516 (Exit 149).

SR 516 lane closure information 

Monday, Nov. 17 through the morning of Tuesday, Nov. 18

  • 8 p.m. to 5 a.m. – One lane in each direction of SR 516 will close overnight between Military Road South and SR 99.

SR 509 Completion Project information

The SR 509 Completion Project builds 3 miles of new tolled highway between I-5 and South 188th Street near the south end of Seattle-Tacoma International Airport. The new highway will be completed in stages. The portion between I-5 and 24th Avenue South opened on June 28 and a new tunnel under I-5 at the SR 516 interchange opened on July 16. The final stage builds the remaining 2 miles of the expressway between 24th Avenue South and South 188th Street. The entire project is planned for completion by 2029.

Photos of construction work are available on the project’s Flickr page. A 3D video tour is also available on WSDOT’s YouTube page.

Puget Sound Gateway Program overview

The SR 509 Completion Project is part of WSDOT’s Puget Sound Gateway Program, which also includes the SR 167 Completion Project in Pierce County. Together, the two completion projects finish critical missing links in Washington’s highway and freight network.

 

Hyperlinks within the release:

SR 167 Completion Project: wsdot.wa.gov/construction-planning/search-projects/sr-167-completion-project

Puget Sound Gateway Program: wsdot.wa.gov/construction-planning/major-projects/puget-sound-gateway-program

3D video tour: www.youtube.com/watch?v=fz6PGrNRaGM

Project’s Flickr page: www.flickr.com/photos/wsdot/collections/72157720074594578/

SR 509 Completion Project: wsdot.wa.gov/construction-planning/search-projects/sr-509-completion-project